岸上电力工程指南

如何为集装箱式岸电系统选择 HVAC 规格

Containerized shore power HVAC sizing should start with the heat that must actually be removed from the conditioned enclosure under the project design condition—not with the converter kVA rating alone.

直接回答: define the real thermal boundary, calculate equipment losses and enclosure heat gains, verify HVAC performance at the site design ambient, check airflow and hot spots, define the one-unit-out operating requirement, and finally verify the thermal design during FAT and commissioning.

A shore power container is not a single heat source. Depending on the architecture, the conditioned enclosure may contain frequency-converter power cells, transformers, reactors, switchgear, control power supplies, UPS equipment, PLC and HMI hardware, lighting and other auxiliaries.

The enclosure itself is also exposed to outdoor temperature, solar radiation, humidity, dust and the marine environment.

A 630 kVA system therefore does not have a 630 kW cooling load, and two 630 kVA shore power packages can require very different HVAC arrangements.

Engineering sizing sequence
Define operating condition → Identify equipment losses → Allocate thermal zones → Add environmental heat gain → Determine cooling duty → Select HVAC at site ambient → Check redundancy → Verify by test
The useful engineering question is not:
“How many air conditioners does a 630 kVA converter need?”

那就是:
“How much heat enters this thermal zone at the worst credible operating condition, how will that heat reach the cooling system, and what operating condition must remain possible if one cooling unit fails?”

Why Converter kVA Is Not the Cooling Duty

Electrical output and thermal loss describe different things.

A frequency converter may transfer hundreds of kilovolt-amperes to a vessel, but only the converter losses become heat inside the equipment space. The same principle applies to transformers, reactors and switchgear: their full electrical rating is not released as heat.

For preliminary engineering, converter efficiency can help estimate loss if the efficiency is known at the relevant operating point.

Converter loss = electrical input power − electrical output power

Where efficiency is known:

Converter loss ≈ output power × (1 / efficiency − 1)

This remains an initial estimate. Final cooling design should preferably use equipment loss data for the actual operating configuration.

A second question must then be answered:

Where does each loss finally go?

If a transformer is installed inside the conditioned enclosure, its heat may belong in that HVAC calculation. If it is installed in a separate ventilated compartment and rejects heat directly outdoors, assigning all of its losses again to the converter-room HVAC would overstate the required duty.

Define the Thermal Boundary Before Calculating Anything

A containerized shore power package can contain several physically different thermal zones:

  • converter room;
  • transformer compartment;
  • medium-voltage switchgear section;
  • low-voltage switchgear section;
  • auxiliary or control compartment;
  • separately ventilated equipment.

Each zone may reject heat differently. The calculation should therefore identify which equipment losses enter the conditioned room and which are rejected somewhere else.

A useful distinction is:

  • Equipment-level cooling moves heat away from components.
  • Enclosure-level cooling removes that heat from the conditioned enclosure and ultimately rejects it outdoors.

A cabinet fan can move heat away from an IGBT module and reduce local component temperature, but if the hot air is discharged into the container, the enclosure HVAC still has to remove that heat.

Two-level cooling for a containerized shore power system
Internal equipment airflow moves heat away from components, while enclosure cooling must ultimately reject the heat from the conditioned space.

For the wider relationship between cabinet airflow and enclosure heat rejection, see our 岸电系统冷却和VHAC设计 指南。.

From Electrical Loss Data to HVAC Selection

Step 1

Define the Design Operating Point

Do not start with only the largest number printed on the equipment nameplate.

Define the expected operating condition:

  • expected vessel load;
  • maximum continuous electrical load;
  • 输入和输出电压;;
  • frequency operating mode;
  • converter operating point;
  • simultaneous auxiliary loads.

A shore power converter operating near full load for long periods can have a different thermal profile from the same converter used mainly at partial load.

Step 2

Prepare an Equipment Loss Schedule

List every meaningful heat-producing device within each thermal zone.

Equipment or Heat SourceRequired Information
Frequency converterLosses at relevant operating load and configuration
变压器No-load and load losses plus installation location
ReactorLoad-dependent losses and thermal location
SwitchgearInternal electrical losses where significant
Control transformerContinuous auxiliary losses
UPS / DC supplyConversion and charging losses
PLC / HMI / controlsContinuous auxiliary heat
FansMotor losses entering the conditioned space
LightingInstalled or expected operating load
Step 3

Allocate Each Loss to the Correct Thermal Zone

This is where an apparently precise calculation can become misleading.

Consider a package with converter cabinets inside an air-conditioned room, a transformer in a separate compartment and an auxiliary cabinet inside the conditioned zone.

Converter and auxiliary losses may enter the conditioned room directly. Transformer losses may not.

If the transformer compartment shares return air with the converter room, however, some or all of its heat may again become part of the HVAC duty.

Important distinction The electrical single-line diagram tells you how power flows. The thermal-zone drawing tells you where heat flows. A complete HVAC calculation may require both.
Step 4

Add Enclosure and Environmental Heat Gain

The enclosure itself exchanges heat with the outdoor environment.

A simplified conductive heat-transfer relationship can be expressed as:

Qenclosure ≈ U × A × ΔT

where:

  • U = overall heat-transfer coefficient;
  • A = effective enclosure surface area;
  • ΔT = indoor-to-outdoor temperature difference.

The direction of heat flow matters. When the outdoor temperature exceeds the required internal temperature, enclosure transmission adds to the cooling load. Under cooler conditions, the enclosure may naturally dissipate part of the internally generated heat.

Solar radiation can add another significant load, especially for outdoor containers exposed directly to the sun.

Step 5

Add Ventilation, Leakage and Moisture Effects Where Applicable

A shore power enclosure is not always completely sealed.

Outside air may enter through:

  • deliberate fresh-air ventilation;
  • equipment openings;
  • cable penetrations;
  • imperfect sealing;
  • doors opened during maintenance;
  • pressure differences caused by fans.

Outside air can introduce both sensible heat and moisture. This can become important in hot and humid coastal environments.

Thermal management is therefore an enclosure-system decision, not merely an air-conditioner selection exercise.

Step 6

Determine the Design Cooling Duty

Qdesign = Qequipment + Qsolar + Qenclosure + Qventilation / infiltration + Qother

The sign and relevance of each term depend on the project.

A useful design record should separately show:

  • calculated internal losses;
  • enclosure heat transfer;
  • solar and environmental heat gains;
  • ventilation or infiltration loads;
  • identified uncertainty;
  • required design reserve.
Step 7

Select HVAC at the Actual Site Condition

Required cooling duty and catalogue cooling capacity are not automatically comparable.

Cooling-unit performance depends on the conditions at which it is rated. The same unit may provide different usable cooling output at different ambient and internal temperatures.

The design basis should therefore identify:

  • maximum outdoor dry-bulb temperature;
  • required internal temperature;
  • 湿度;;
  • solar exposure;
  • dust and contamination;
  • salt-laden atmosphere;
  • altitude where relevant.

The selected HVAC capacity should then be checked against the manufacturer's performance data at those project conditions.

For marine environmental measures, see our 岸电腐蚀和防盐雾保护 文章.

Step 8

Check the One-Unit-Out Condition

Only after the normal cooling duty has been established does redundancy become meaningful.

If one HVAC unit becomes unavailable, the project has to define what the shore power system is expected to do.

Do Not Hide Margin Inside an Arbitrary Oversizing Factor

Engineering margin is necessary because equipment does not operate forever under clean catalogue conditions.

Cooling performance can be affected by:

  • filter loading;
  • fouling;
  • airflow resistance;
  • partial recirculation;
  • equipment ageing;
  • uncertainty in electrical losses;
  • solar-load variation;
  • installation tolerances.

These conditions justify reserve, but the reason for that reserve should remain visible.

A more defensible sizing record separates: calculated thermal duty, identified uncertainty, degradation allowance, design reserve, cooling performance at the project ambient, and post-failure cooling requirement.

A generic rule such as “multiply the cooling load by 1.3” is not automatically a better design unless the factor has a defined engineering basis.

Airflow Is Part of the Thermal Design

Cooling capacity answers one question:

Can enough heat theoretically be removed?

Airflow answers another:

Can the heat actually reach the cooling system without overheating equipment on the way?

Poor airflow can produce local thermal failure even when the total installed HVAC capacity appears adequate.

Important areas include:

  • converter cabinet air inlets;
  • cabinet exhausts;
  • hot-air return paths;
  • partitions;
  • cable trenches;
  • raised floors;
  • equipment clearances;
  • wall-mounted HVAC units;
  • condenser intake and discharge locations.
Containerized shore power system with external HVAC equipment
Physical layout affects equipment air intake, hot-air return, HVAC access, condenser airflow and the risk of local recirculation.

One engineering configuration used relatively short and wide airflow paths through the converter power-unit area, with air entry around the cabinet and high-volume fans at the upper section.

The lesson is not that every project should copy that cabinet geometry. It is that equipment airflow and enclosure heat rejection must be engineered together.

Why Adequate Cooling Capacity Can Still Overheat in Service

Hot-Air Recirculation

If hot discharge air returns directly to the equipment intake, the effective inlet temperature increases. The room may still have enough theoretical refrigeration capacity while the converter receives air that is too warm.

Blocked or Restricted Airflow

Filters, cable routing, temporary materials or later installation changes can restrict airflow after commissioning. The calculated heat load has not changed, but the heat-transfer path has.

Poor Sensor Location

One room-temperature sensor may not represent every thermal zone. A normal reading near the return-air path can exist at the same time as a hotter converter inlet or upper cabinet zone.

Condenser Recirculation

Outdoor condenser airflow also matters. One condenser should not discharge heated air directly into the intake of another cooling unit.

Loss of a Common Auxiliary Supply

Several cooling devices can be mechanically independent while still depending on the same electrical feeder or control source.

Standby Humidity

When the converter operates, its losses naturally warm the enclosure. When it is idle, that heat disappears. In a humid environment, the dominant problem may then change from overheating to condensation control.

N+1 Cooling Is a Performance Requirement, Not an Equipment Count

“N+1 HVAC” is incomplete unless the required system condition after one cooling-unit failure has been defined.

Full-Output Continuity

One HVAC unit is unavailable, but the remaining equipment must keep the enclosure within the approved thermal limits while the shore power system remains at full specified output.

Derated Operation

Remaining cooling capacity can support continued operation only after electrical output is reduced to a defined level.

Time-Limited Operation

Thermal inertia allows continued operation for a defined period, followed by controlled shutdown if cooling is not restored.

Available cooling after the defined failure ≥ required post-failure cooling duty

Both sides of the comparison must use the same project ambient condition and the same defined electrical load.

Installing an additional air conditioner does not, by itself, demonstrate useful N+1 performance.

Common-Mode Failure Can Defeat Cooling Redundancy

Redundancy needs to be checked across the complete cooling chain.

Four air-conditioning units supplied from one auxiliary feeder may appear mechanically redundant, but the feeder can remain a single point of failure.

同样的原理也适用于:

  • common control power;
  • shared HVAC controller;
  • common breaker;
  • shared fan supply;
  • common communication dependency;
  • shared condenser or airflow constraints.

In one shore power engineering configuration, the converter cooling fans were provided with two alternative power sources. That design was project-specific, but it illustrates the underlying principle:

Cooling redundancy should be evaluated from the failure boundary—not from equipment count alone.

Coordinate Cooling Faults With the Operating State

HVAC and fan faults are part of the electrical operating system, not merely building-service alarms.

The control system may need to monitor:

  • HVAC running status;
  • HVAC fault;
  • converter cooling fan status;
  • transformer fan status;
  • enclosure temperature;
  • transformer temperature;
  • auxiliary cooling power;
  • filter condition where monitored;
  • condensate alarm where relevant.

The required response then depends on the remaining thermal capability.

Example response philosophy
Cooling fault → Operator alarm → Temperature supervision → Derating / restricted operation → Shutdown at approved limit
Shore power cooling fan power and fault response logic
Cooling failure should be coordinated with temperature monitoring, alarm logic and the project-defined operating response.

In one reference configuration, cooling failure generated local and remote alarms while the converter could initially remain in service. If the condition was not corrected and temperature reached the configured upper limit, the converter stopped.

The important engineering point is that a cooling fault and an overtemperature trip are not necessarily the same event.

Project Evidence: What a 630 kVA Configuration Actually Tells Us

One 630 kVA shore power configuration used four customized 5P industrial air-conditioning units for enclosure cooling.

That is useful engineering evidence, but it does not create a general relationship such as:

630 kVA = four 5P air conditioners

The useful lesson is that HVAC quantity only becomes meaningful after the project has already established:

  • equipment arrangement;
  • internal heat sources;
  • thermal-zone boundaries;
  • enclosure configuration;
  • cooling method;
  • project environmental condition.

Another 630 kVA package may place the transformer outside the conditioned enclosure and therefore present a lower internal heat load.

A different 630 kVA project may operate in a hotter environment, experience greater solar gain or require full electrical output after one HVAC unit fails, resulting in a higher installed cooling requirement.

The electrical rating stayed the same.

The thermal design did not.

What the 4 × 5P Configuration Does Not Prove

The project example does not by itself prove:

  • the heat loss of every 630 kVA converter;
  • a universal design ambient temperature;
  • a universal redundancy requirement;
  • a universal 5P cooling capacity;
  • a universal number of HVAC units;
  • that another port should use the same configuration.

A technically credible proposal should distinguish between a proven project configuration and a reusable engineering calculation method.

Thermal Design Should Produce Acceptance Evidence

HVAC engineering is not complete when the cooling equipment is ordered.

The calculation should produce documentation that can later be checked during FAT and commissioning.

证据What It Verifies
Approved equipment loss scheduleHeat-generation basis
Thermal-zone drawingWhich losses belong to each cooling boundary
Airflow drawingSupply, return and equipment airflow paths
HVAC performance curveAvailable cooling capacity at project conditions
Auxiliary-power diagramCommon-mode cooling failure boundaries
Temperature sensor scheduleWhich thermal conditions are actually monitored
Cause-and-effect matrixAlarm, derating and shutdown behavior
FAT thermal recordActual temperature response under the test load
Commissioning recordInstalled airflow, controls and thermal response

This evidence chain is more useful than a specification that simply says “industrial air conditioning, N+1.”

Verify Cooling During FAT

FAT should verify both the physical cooling arrangement and the control response.

Relevant checks can include:

  • fan rotation and airflow direction;
  • fan running status;
  • HVAC start and stop;
  • staged operation;
  • duty/standby changeover where provided;
  • HVAC fault;
  • fan fault;
  • high-temperature alarm;
  • temperature protection;
  • control-system indication;
  • defined derating or shutdown functions.

A sustained load test provides stronger thermal evidence than brief energization because transformers, reactors, cabinets and the enclosure itself require time to approach a meaningful thermal condition.

Useful test data include:

  • electrical load;
  • 环境温度;;
  • internal enclosure temperature;
  • converter inlet-air temperature where monitored;
  • transformer or reactor temperature where applicable;
  • active cooling units;
  • fan states;
  • elapsed operating time.

For the wider outdoor power-package arrangement, see our 集装箱式岸上供电系统 页面.

A Cool Factory Test Does Not Prove a Hot-Site Design

Suppose the project thermal design condition is a high outdoor temperature, but FAT is performed in a much cooler factory.

The converter reaches full load and every recorded temperature remains acceptable.

That is useful evidence.

It is not, by itself, proof that the same enclosure will remain inside its thermal limits at the maximum project ambient.

Two important conditions have changed:

  1. the heat exchange through the enclosure surface;
  2. the cooling performance available from the HVAC equipment.

The stronger engineering assessment combines:

FAT temperature evidence + Verified equipment losses + HVAC performance at project ambient + Enclosure thermal calculation

What Should Be Recorded at Thermal Stabilization?

A useful acceptance record should not say only:

“System operated normally.”

The operating conditions need to be recorded so that the result can be interpreted later.

Consider recording:

  • actual electrical load or load percentage;
  • input/output operating mode;
  • 环境温度;;
  • internal enclosure temperature;
  • representative cabinet inlet temperature;
  • transformer temperature where applicable;
  • operating HVAC units;
  • disabled HVAC units during redundancy testing;
  • 粉丝状态;;
  • time from load application to stabilized reading;
  • alarm state;
  • derating or trip state.

A temperature value without the operating condition has limited engineering meaning.

For example, an enclosure temperature of 35°C can describe an excellent result at high load and high ambient—or a weak result at low load in a cool factory.

Context turns the measurement into evidence.

Common HVAC Sizing Errors

Sizing From Converter kVA Electrical output capacity is not internal thermal loss.
Counting Internal Fan Airflow as HVAC Capacity Internal fans move heat but do not necessarily reject it outdoors.
Mixing Thermal Zones Equipment in separate ventilated compartments should not automatically be assigned to one HVAC calculation.
Ignoring Solar Gain Outdoor enclosure heat gain can increase even when electrical load remains unchanged.
Using Catalogue Capacity at the Wrong Ambient HVAC output should be checked against the actual project condition.
Applying an Unexplained Safety Factor Margin should respond to identifiable uncertainty.
Calling Equipment N+1 Without Checking Duty Installed unit count does not define post-failure system capability.
Ignoring Common Auxiliary Failure Several cooling devices can still share one electrical failure point.
Checking Only Average Room Temperature Local cabinet hot spots can exist behind a normal room-temperature measurement.
Ignoring Standby Humidity The worst temperature condition and worst condensation condition may occur at different times.

Information Needed Before HVAC Sizing

For a containerized shore power project, thermal inputs are more useful than the converter rating alone.

Electrical and Equipment Data

  • converter rating;
  • expected load profile;
  • converter loss data;
  • 变压器损耗;;
  • transformer installation location;
  • reactor losses;
  • switchgear losses where relevant;
  • UPS and auxiliary loads.

Enclosure Data

  • container dimensions;
  • equipment arrangement;
  • thermal-zone boundaries;
  • wall and roof construction;
  • insulation;
  • openings;
  • cable penetrations;
  • planned ventilation.

Environmental Data

  • maximum outdoor temperature;
  • minimum outdoor temperature where relevant;
  • 湿度;;
  • solar exposure;
  • altitude;
  • 灰尘;;
  • salt-fog conditions.

操作要求

  • permissible internal temperature;
  • equipment inlet-air limits;
  • standby environmental requirements;
  • allowable reduced-load operation;
  • required output after one HVAC failure;
  • allowable time before shutdown.

HVAC Data

  • rated cooling capacity;
  • performance curve versus ambient temperature;
  • air volume;
  • filtration;
  • condenser arrangement;
  • auxiliary power;
  • alarm and control interface.

Verification Requirements

  • FAT load;
  • FAT duration;
  • required sensor locations;
  • temperature acceptance criteria;
  • one-unit-out test requirements;
  • alarm and shutdown tests;
  • commissioning verification.

常见问题解答

是否可以通过转换器的效率来估算HVAC的容量?

是的,用于初步工程。 V经验证的效率和运行负荷可以提供早期转换器损耗的估算值。最终的尺寸设计仍应包括其他设备损耗、箱体热传递、环境热量增加以及实际的热区布置。.

每个集装箱式岸上电力系统都需要空调吗?

不。根据设备和环境的不同,该封装可能采用强制通风、空调、换热器、闭环冷却或其他工程化的热管理方法。.

630 kVA 的额定功率是否决定了 HVAC 的容量?

不正确。电气规格并不定义内部损耗、外壳热量增加、现场环境条件或冗余目标。.

4 台 5P 空调机组是否是 630 kVA 系统的标准配置?

不。在某一项目配置中使用了四台定制的 5P 单元。该设备数量具体取决于项目的机箱和散热方案,不应被视为通用的尺寸计算规则。.

N+1 HVAC到底是什么意思?

这意味着在特定故障情况下具备额外的冷却能力。剩余设备仍需根据所需的故障后电气负载和项目环境条件进行检查。.

如果箱体温度仍然正常,是否可以忽略一个VHAC故障?

Not automatically. Temperature may rise slowly because of thermal inertia. The project should define the required alarm, monitoring, derating and shutdown response while the remaining cooling capability is assessed.

Should HVAC operate when the converter is idle?

Possibly. Standby heating, ventilation or dehumidification may still be required where humidity or condensation could move outside acceptable equipment conditions.

Does a successful full-load FAT prove HVAC capacity at site?

Not always. If FAT ambient conditions are less severe than the project design condition, the test should be combined with verified heat losses, enclosure thermal calculations and HVAC performance data at the project ambient.

What thermal data should be recorded during FAT?

Record the electrical load, ambient temperature, internal temperatures, relevant equipment temperatures, active HVAC units, fan status and sufficient operating time to show a meaningful thermal condition.

技术参考

  1. IEC/IEEE 80005-1:2019 — High Voltage Shore Connection Systems , including its published amendments.
  2. IEC/IEEE 80005-3:2025 — Low-Voltage Shore Connection Systems .
  3. Rittal technical guidance on enclosure thermal management and cooling calculation .
  4. Schneider Electric enclosure cooling-unit performance guidance .

Scope note: shore-connection standards define the wider electrical system framework. They do not establish a universal rule such as “X kVA requires Y tons of HVAC.” Thermal sizing still depends on the actual equipment losses, enclosure arrangement, environmental conditions and required post-failure operation.

Send the Thermal Design Inputs, Not Only the Converter Rating

Send the equipment loss schedule, enclosure layout, thermal-zone arrangement, outdoor design conditions, required internal temperature and cooling-redundancy target. SDACME can review the heat-rejection boundary, cooling duty, airflow arrangement, HVAC performance, auxiliary-power dependency, alarm response and thermal verification requirements as part of the shore power system engineering review.

Send Thermal Design Inputs