Shore Power Technical Article · Electrical Acceptance

Insulation Withstand and Protection Relay Tests for Shore Power

Shore power electrical acceptance must prove dielectric integrity, measurement correctness, protection behaviour and the complete trip path. A test result is meaningful only when its boundary, configuration and acceptance evidence match the equipment that will actually enter service.

Engineering answer: define the electrical boundary before selecting the test condition, verify the measurement path before testing relay behaviour, and prove the complete protection path rather than the relay alone.

Electrical acceptance of a shore power system has to prove more than one thing.

An insulation test verifies whether a defined part of the electrical system has acceptable insulation condition or dielectric strength. A protection test verifies whether an abnormal electrical condition is detected and whether the required trip or control action follows.

Neither result should be treated in isolation.

A shore power system should not be accepted simply because an insulation-resistance value looks high, a withstand-test sheet says “pass,” or a protection relay responds to a secondary-injection signal. The test boundary, measurement path, approved settings, trip circuit, breaker action and final records all have to represent the equipment that will actually enter service.

Core engineering principle: define the electrical boundary before selecting the test condition, and prove the complete protection path rather than the relay alone.
shore power frequency converter factory acceptance test
Factory acceptance testing establishes a controlled electrical and functional baseline before equipment is transported and integrated at site.

Electrical Acceptance Is a Sequence, Not a Single Test

A shore power package can combine switchgear, transformers, frequency-conversion equipment, busbars, cables, CTs, VTs, protection relays, auxiliary supplies, interlocks and supervisory controls.

Testing these components individually is necessary, but it does not automatically prove that the complete system is ready for energization.

A practical acceptance sequence moves through several layers:

  1. Equipment and parameter verification
  2. Wiring and secondary-circuit inspection
  3. Insulation-condition verification
  4. Applicable dielectric withstand testing
  5. CT/VT and measurement-path verification
  6. Protection-relay functional testing
  7. Trip-path and breaker-operation verification
  8. Interlock, alarm and feedback verification
  9. Integrated operating checks
  10. Acceptance-record review and closeout

Acceptance evidence builds layer by layer

Equipment→ Wiring→ Insulation→ Measurement→ Relay→ Trip Path→ Integrated Operation→ Accepted Record

This sequence reflects an important engineering distinction. A relay test assumes that the signal reaching the relay is meaningful. A breaker trip test assumes that the protection output reaches the trip circuit. A withstand test assumes that the intended electrical boundary has been created correctly.

Each layer depends on evidence established by the layers around it.

Define the Test Boundary Before Applying Voltage

A complete shore power installation can contain medium-voltage or low-voltage switchgear, transformers, frequency converters, busbars, cables, metering circuits, protection relays, surge-protection equipment, auxiliary supplies and control electronics.

These components do not automatically belong inside the same dielectric test boundary.

Before an insulation or withstand test begins, identify exactly which conductors and equipment are included. The review should use the final single-line diagram, wiring drawings, equipment voltage classes, applicable standards, manufacturer instructions and the actual connection state.

This becomes particularly important around power electronics and measurement circuits. A test suitable for a switchgear main circuit may not be suitable for a voltage transformer, surge protective device, converter power section or sensitive control circuit.

shore power insulation test boundary and protection relay trip path
The withstand-test boundary and protection-verification path are different engineering boundaries. Both need to be defined explicitly.

One shore power test procedure, for example, required deliberate treatment of voltage-transformer circuits, surge arresters, incoming and outgoing cables and transformer connections before withstand testing.

The engineering lesson is more important than any project-specific voltage value: a withstand voltage is meaningful only after the test object has been defined.

For the wider equipment verification sequence, see our shore power manufacturing and FAT guidance.

What Each Electrical Test Can—and Cannot—Prove

An acceptance programme becomes much clearer when each test is defined by its evidence boundary.

Test or verificationWhat it can proveWhat it does not prove by itself
Insulation resistanceCondition of insulation within the measured boundaryDielectric withstand under an elevated AC test
Power-frequency withstandDielectric capability of the approved test boundaryCondition of every device excluded from that boundary
CT/VT verificationRatio, polarity, wiring and measurement-path correctnessRelay timing or breaker trip performance
Secondary injectionRelay pickup, timing, logic and outputsComplete primary measurement and downstream trip chain
Breaker functional tripTrip circuit and breaker responseCorrect relay settings or CT polarity
Feedback verificationCorrect position and status indicationMechanical condition under every possible fault scenario
FAT integrated testFactory baseline of assembled equipmentSite interfaces added after transportation and installation
SAT verificationInstalled condition and changed interfacesEvery factory test necessarily needs to be repeated

This distinction prevents a common acceptance mistake: using evidence from one test to make a conclusion that belongs to another test.

Insulation Resistance Shows Condition, Not Full Withstand Capability

Insulation resistance and dielectric withstand are related, but they answer different engineering questions.

An insulation-resistance test applies a defined DC test voltage and measures resistance between selected conductors and earth or between circuits.

It can help identify abnormal condition associated with:

  • Moisture
  • Contamination
  • Damaged insulation
  • Incorrect installation
  • Unintended electrical connection

But a high resistance value does not automatically demonstrate that the equipment has passed the required power-frequency withstand test.

The measurement record should identify the circuit tested, the test boundary, test voltage, equipment condition and result. Comparing results only makes sense when the test conditions are understood.

Insulation resistance is condition evidence. It is not a substitute for dielectric withstand verification where withstand testing is required.

Power-Frequency Withstand Testing Requires a Controlled Boundary

A power-frequency withstand test applies an elevated AC voltage to a defined circuit for the required duration to demonstrate dielectric strength.

The applicable test condition depends on:

  • Equipment voltage class
  • Equipment type
  • Applicable standard
  • Insulation system
  • Previous equipment testing
  • Project specification
  • Factory or installed test condition

Transformer insulation tests, switchgear tests and assembled-system tests can therefore have different boundaries and requirements.

The correct question is not “what voltage should be applied to the shore power system?” It is which equipment is being tested, under which requirement, and what is connected to that test boundary?

Sensitive Components Can Change the Entire Test Plan

A stricter electrical test is not automatically a better test.

Power semiconductor circuits, voltage transformers, surge-protection devices, measurement networks and communication electronics do not necessarily share the same withstand capability as the main power circuit.

When the boundary is too broad

Sensitive equipment can remain connected and be exposed to an inappropriate test condition.

When the boundary is too narrow

Part of the actual insulation system that should have been verified can be accidentally excluded.

Before testing, review:

  • Main power circuit
  • Measurement circuits
  • Protection inputs
  • Auxiliary power
  • SPDs or surge arresters
  • PT/VT connections
  • Converter interfaces
  • External cables
  • Earthing arrangements
  • Manufacturer-required disconnections

Protection Verification Starts Before the Relay Test

Protection testing should not begin by assuming that the relay input is already correct.

Before relay behaviour can be trusted, the measurement path should be verified.

This includes:

  • CT identification
  • CT ratio
  • CT polarity
  • Secondary wiring
  • VT identification and ratio
  • VT polarity where relevant
  • Secondary grounding
  • Terminal assignment
  • Scaling in the relay or control system

A project-specific shore power test procedure illustrates this sequence clearly: current measurement channels were checked using controlled simulated quantities before protection behaviour was verified.

Verify sensing → verify scaling → verify protection pickup → verify final action.

Why CT and VT Errors Matter So Much

Current transformers and voltage transformers connect the physical power system to protection, metering and control. Errors in this interface can create faults that are difficult to recognize because the protection relay itself may remain completely healthy.

Incorrect CT ratio

The relay receives a correctly shaped signal at the wrong magnitude.

Reversed CT polarity

Directional or power-based protection can interpret power flow incorrectly.

Wrong phase assignment

The relay can associate an electrical condition with the wrong phase.

VT scaling error

Voltage, power or directional calculations can become incorrect.

Incorrect secondary grounding

The measurement circuit may no longer behave as designed.

Use Secondary Injection to Verify Relay Behaviour

Secondary injection supplies controlled quantities directly to the protection device.

It is useful because engineers can test protection behaviour without creating an actual high-energy primary fault.

Depending on the function under test, secondary injection can verify:

  • Pickup threshold
  • Timing
  • Inverse-time behaviour
  • Instantaneous operation
  • Voltage protection
  • Frequency protection
  • Output contacts
  • Indications
  • Alarms
  • Internal logic

One project test procedure used a protection test instrument to inject secondary current and verify inverse-time and instantaneous protection behaviour.

The important evidence is not the project-specific current multiple. It is the verification method: known input → expected response → measured response → recorded result.

For the wider relationship between protection functions and interlock logic, see our shore power protection and interlock functions guide.

Relay PASS Does Not Mean Protection System PASS

A relay can operate correctly while the actual system fails to reach the required safe state.

Relay PASS ≠ Protection System PASS.
A successful relay response does not automatically prove the CT/VT path, trip wiring, auxiliary supply, breaker operation, feedback or event recording.

A simplified protection path may be represented as:

CT / VT→ Relay→ Protection Logic→ Trip Circuit→ Breaker→ Feedback→ Event Record

Possible hidden failures include:

  • Loose or incorrect wiring
  • Missing auxiliary trip supply
  • Defective intermediate relay
  • Open trip circuit
  • Failed breaker trip coil
  • Breaker mechanical failure
  • Incorrect auxiliary-contact feedback
  • Missing alarm or event record

Prove the Complete Trip Path

Where practical, a functional protection test should follow the chain far enough to demonstrate the intended system response.

  1. Initiating measurement or simulation
  2. Relay detection
  3. Output contact operation
  4. Intermediate logic
  5. Trip-power availability
  6. Breaker trip-coil operation
  7. Actual breaker opening
  8. Open-position feedback
  9. Alarm indication
  10. Event or first-out record

If a part of the chain is simulated rather than physically tested, the simulation boundary should be identified in the test record.

shore power switchgear protection relay breaker integration
Protection verification extends beyond the relay to switching, trip, auxiliary-power and feedback interfaces that have to operate as one system.

The equipment functions behind these actions are discussed further in our shore power input and output switchgear guide.

Test the Action and the Evidence of the Action

A protection event creates two outputs: the physical response and the record of what happened.

If a breaker opens correctly but the control system reports the wrong initiating condition, the immediate electrical hazard may be removed while future diagnosis becomes unreliable.

If the breaker opens but open-position feedback remains false, the control system may not recognize that the intended safe state has been reached.

Where applicable, verify:

  • Physical action
  • Position feedback
  • Alarm text
  • Event timestamp
  • First-out information
  • Reset behaviour

Protection Settings Are Part of the Acceptance Evidence

A relay can pass every functional test and still be configured incorrectly for the project.

Protection settings should come from an approved protection or coordination basis. They should not be copied from technician habit, another berth, another vessel, a similarly rated converter or an outdated settings file.

A controlled test record can include:

  • Relay model and device identification
  • Firmware revision
  • Settings revision
  • CT/VT ratios
  • Enabled functions
  • Pickup and timing settings
  • Test-set identification
  • Calibration status
  • Expected result
  • Measured result
  • Final loaded configuration

A result is only valid for the configuration that was actually tested.

A Good Test Report Records More Than PASS

A future engineer should be able to understand the acceptance decision after the original test team has left.

The record should make it possible to reconstruct:

  • What was tested
  • What was connected and disconnected
  • What instrument was used
  • What configuration was active
  • What result was expected
  • What result was observed
  • Whether any deviation occurred
  • How the deviation was resolved
  • Which final revision was accepted
A test should remain understandable after the test team leaves. “PASS” alone does not preserve that engineering evidence.

What to Do When a Test Does Not Match the Expected Result

Acceptance testing is not a process of repeatedly running the same test until a passing result appears.

A nonconforming result should trigger a controlled closeout process:

Observation→ Cause Investigation→ Corrective Action→ Affected-Scope Retest→ Record Update→ Acceptance
ObservationEngineering meaningAppropriate response
Insulation resistance is lower than the factory baselineBoundary, contamination, moisture, termination or insulation condition may have changedConfirm the boundary and investigate before energization
Relay pickup is outside expected toleranceSettings, scaling, test connection or relay behaviour may be incorrectVerify configuration and repeat the controlled test
Relay operates but breaker remains closedThe downstream trip path has not been provenInspect trip power, wiring, intermediate relay, trip coil and breaker
Breaker opens but feedback remains closedThe physical action works but the feedback chain does notVerify auxiliary contacts, wiring and point mapping
CT polarity is reversedDirectional or power-related functions may be invalidCorrect wiring and repeat all affected tests
Settings file differs from the approved revisionPrevious test evidence may no longer represent the final designResolve the revision and repeat affected functions
SAT boundary differs from FATFactory test evidence cannot be copied blindlyDefine the correct installed test scope

Acceptance Evidence Has Dependencies

One correction can invalidate more than one previous test result.

If CT wiring is changed

Measurement verification, relay tests, directional protection and affected power calculations may need to be repeated.

If protection settings are changed

Previously recorded pickup and timing tests may no longer represent the delivered configuration.

If a trip circuit is rewired

Breaker functional tests, feedback and alarm verification should be reconsidered.

If a cable termination is repaired

The insulation evidence for that affected circuit may need to be repeated.

FAT Establishes the Factory Baseline

Factory acceptance testing provides a controlled environment before the equipment is transported to site.

The factory stage can establish evidence for:

  • Equipment identity
  • Wiring condition
  • Insulation boundary
  • Applicable dielectric tests
  • CT/VT circuits
  • Protection-relay functions
  • Internal trip circuits
  • Breaker operation
  • Interlocks and alarms
  • Control logic
  • Settings revisions
  • Recorded results

Loaded operating tests can then add another evidence layer by showing whether measurement, control and protection remain coherent during actual system operation.

Transport and Installation Create a New Electrical State

The equipment that arrives at site is not electrically identical to the factory test setup.

Between FAT and energization:

  • Cabinets are transported
  • Cables are installed
  • Terminations are completed
  • Switchgear sections may be reconnected
  • Field CT/VT circuits are connected
  • Auxiliary supplies change source
  • Berth interfaces are added
  • Communication links are commissioned
  • External trip and interlock circuits are introduced

FAT evidence remains important, but it does not eliminate site verification.

SAT Should Target the Changed Boundary

The role of SAT is to identify what may have changed since the factory baseline.

Depending on the project, relevant site checks can include:

  • Insulation condition
  • Cable insulation
  • Wiring continuity
  • Termination condition
  • Phase sequence
  • CT/VT wiring
  • Polarity
  • Field trip circuits
  • Breaker operation
  • Remote feedback
  • External interlocks
  • Communication interfaces
  • End-to-end protection operation
SAT should not be a blind copy of FAT. Site testing should target the electrical boundaries and interfaces that changed during transport, installation and integration.

FAT → Installation → SAT Should Form One Evidence Chain

FAT Baseline→ Transport→ Installation Changes→ SAT Verification→ Anomaly Closeout→ Final Acceptance

The strongest acceptance package links all stages instead of treating FAT and SAT as unrelated folders of test reports.

Final acceptance should confirm that factory evidence remains applicable, changed interfaces have been verified, anomalies are closed, settings are controlled and the test record represents the delivered equipment.

Loaded Operation Adds Another Verification Layer

After electrical integrity and protection functions have been checked, loaded operation can provide additional system-level evidence.

A project test programme can include progressive loading, full-load operation, overload behaviour, stability monitoring and periodic recording of electrical parameters.

These tests do not replace insulation or protection verification. They show whether measurement, protection and control remain coherent when the system operates.

Detailed harmonic and waveform analysis belongs to the dedicated shore power harmonic-testing article.

Common Shore Power Acceptance Errors

Applying one test voltage to the entire connected package

Different equipment can have different dielectric requirements and test boundaries.

Treating insulation resistance as a withstand test

A high resistance value does not replace dielectric verification.

Testing the relay before confirming its inputs

The relay can respond correctly to an incorrect CT/VT configuration.

Verifying relay output but not breaker action

Wiring, auxiliary supply or trip-coil failures can remain hidden.

Confirming breaker action but ignoring feedback

The physical state and reported state can disagree.

Using an unapproved protection-settings revision

The test can prove behaviour that does not correspond to the final design.

Repeating SAT tests without checking the installed boundary

Equipment added after FAT may change the applicable site test condition.

Recording only “PASS”

Future engineers cannot reconstruct the acceptance decision.

Fixing a problem without retesting dependent functions

One correction can invalidate several previous results.

Treating FAT and SAT as unrelated documents

The site team loses the baseline needed to understand what changed.

What Should a Traceable Acceptance Record Contain?

Evidence itemWhat should be identifiable
Test objectEquipment, feeder or circuit
Test purposeThe engineering question the test answers
Electrical boundaryConnected, isolated and disconnected equipment
Applicable requirementStandard, specification or approved procedure
Equipment conditionFAT, installed SAT state or maintenance condition
InstrumentIdentification and calibration status
Measurement configurationCT/VT ratios, wiring and scaling
Protection configurationSettings revision and enabled functions
Applied quantityVoltage, current, frequency or simulation
Expected resultAcceptance value, timing or required action
Actual resultMeasured value or observed action
Trip-path resultFinal controlled-device action
Feedback resultBreaker state, alarm and event record
DeviationAbnormal observation or simulation boundary
Corrective actionWhat changed and why
Retest scopeWhich evidence was repeated after correction
Final acceptanceResponsible approval and final status

Information Needed Before Preparing the Test Schedule

  • Final single-line diagram
  • Primary wiring drawings
  • Secondary wiring drawings
  • Voltage classes
  • Converter architecture
  • Transformer specification
  • Switchgear specification
  • Cable and termination information
  • Manufacturer test limitations
  • Applicable equipment standards
  • Approved withstand criteria
  • Protection study
  • Approved protection settings
  • CT and VT ratios and polarity
  • Breaker trip circuits
  • Interlock cause-and-effect matrix
  • External trip interfaces
  • SCADA feedback requirements
  • FAT and SAT responsibilities
  • Witness points
  • Test-equipment and calibration requirements
  • Final acceptance-record format

These inputs determine not only which tests should be performed, but also which results remain valid when the system configuration changes.

Frequently Asked Questions

Is an insulation-resistance test the same as a withstand test?

No. Insulation resistance evaluates insulation condition using a defined DC test voltage. A power-frequency withstand test demonstrates dielectric capability of a defined electrical boundary under an approved elevated AC voltage.

Can a protection relay be tested without primary fault current?

Yes. Secondary injection can verify pickup, timing, logic, outputs and indications by supplying controlled quantities directly to the protection device. It does not automatically verify the complete CT-to-breaker protection chain.

Does secondary injection prove the complete protection system?

No. Additional checks may be needed for CT/VT circuits, trip wiring, auxiliary power, breaker action, feedback and event recording.

Does a breaker opening prove the entire protection function?

Not necessarily. The breaker may operate correctly while measurement scaling, relay settings, feedback or alarm recording remain incorrect.

Should every FAT withstand test be repeated during SAT?

No. SAT should first determine what changed during transportation, cable installation, termination and site integration. Any site high-voltage test should follow the approved equipment and project procedure.

What happens if a relay setting changes after FAT?

Identify which previous results depend on that setting and repeat the affected protection tests so the final acceptance evidence represents the delivered configuration.

Why is recording the actual measured result important?

Because the result may later be needed to compare against a factory baseline, investigate degradation or confirm exactly what was accepted. “PASS” alone does not preserve that engineering evidence.

Technical References

The applicable edition and project scope should always be confirmed before use.

  1. IEC/IEEE 80005-3:2025 — Low-voltage shore connection systems.
  2. IEC/IEEE 80005-1:2019+A1:2022+A2:2023 — High-voltage shore connection systems.
  3. IEC 60255-1:2022 — Measuring relays and protection equipment — Common requirements.
  4. IEC 60255-151:2009 — Functional requirements for over/under-current protection.
  5. IEC 60076-3:2013+A1:2018 — Power transformer insulation levels and dielectric tests.
  6. IEC 62271-200:2021+A1:2024 — AC metal-enclosed switchgear above 1 kV up to and including 52 kV.

Agree the Electrical Acceptance Boundary Before Testing Begins

A useful shore power test programme does not begin with a generic list of withstand voltages or relay-test multiples. It begins with the actual electrical architecture.

Send the single-line diagram, voltage classes, transformer and switchgear data, protection study, relay settings, CT/VT data, trip matrix, FAT/SAT responsibilities and required witness points.

SDACME can review these inputs as one acceptance system—connecting insulation boundaries, measurement paths, protection functions, trip verification, site changes and final acceptance records into a traceable engineering review.

Send Your Electrical Test Requirements